Turn time is mostly waiting, not working. On a typical 12-day turn, actual trade hours account for three to four days. The rest is scope delay, material delay, and handoff gaps.
Where the days go
| Cause | Days lost | Fix |
|---|---|---|
| Scope written after keys drop | 2–4 | Pre-move-out walk at notice |
| Materials not on hand | 2–5 | Building-standard SKUs, small on-site stock |
| Sequential bidding | 1–3 | Standing per-unit pricing with one vendor |
| Trade handoff gaps | 2–4 | Pre-scheduled sequence, not per-call scheduling |
| Multiple partial walkthroughs | 1–2 | One punch walk |
| Discovered water damage | 3–10 | Check under sinks and at tub deck at the walk |
Safe accelerators
- Standardize everything. One paint color and sheen, one flooring SKU, one hardware finish, one door style.
- Stock the shop. Blinds, outlet covers, hardware, two boxes of the flooring, a five-gallon of the standard paint.
- Book the sequence before keys drop. Trades get calendar slots, not phone calls.
- Spray-and-backroll full repaints instead of cut-and-roll.
- Swap planks instead of replacing rooms — the reason single-SKU LVP is worth the spec.
- Photograph once, thoroughly, and scope from photos the same day.
- One punch walk with a written list.
Shortcuts that cost you later
Painting over water stains. It comes back by February, and if it fails an inspection you own both the repair and the finding.
Skipping caulk at the tub deck. Buys you an hour, costs a subfloor.
Not priming drywall patches. Flashing shows through, and the wall gets repainted anyway.
Reusing a worn wax ring or leaving a rocking toilet. A rocking toilet is a slow leak with a schedule.
Bypassing alarm testing. Smoke and CO alarms are a life-threatening finding on inspection and a liability exposure. Test and log every turn, every time.
Not checking bath fan airflow. Cited constantly, and it drives moisture and ice dam problems.
Skipping the GFCI test. Ten seconds. Common finding.
Deferring "we will get it on the next turn." Nobody does.
The five-minute compliance pass
Add this to the end of every turn, before punch:
- Test smoke and CO alarms; write the date on the unit
- Test GFCIs at kitchen, bath, and exterior
- Open every bedroom window fully and confirm egress
- Hold a tissue to each exhaust fan
- Check under both sinks with a flashlight
- Confirm range anti-tip bracket
- Confirm all supply stops turn
Seven items, five minutes, and it covers most of what gets cited.
Turns run to a standard
We do Twin Cities apartment make-ready with per-unit pricing, a fixed sequence, and a documented punch and compliance pass on every unit.
Licensed MN remodeler QC807391, insured. Call 612-400-8036.
Want an exact number for your project?
Free on-site estimate across the Twin Cities metro — no pressure, no obligation.
Frequently asked questions
Why do apartment turns take so long?
Most of the time is waiting, not working — scope written after keys drop, materials not on hand, sequential bidding, and gaps between trade handoffs. Actual trade hours are usually three to four days.
What turn shortcuts cause problems later?
Painting over water stains, skipping tub-deck caulk, not priming drywall patches, leaving a rocking toilet, and skipping alarm and GFCI testing.
What should be checked at the end of every turn?
Smoke and CO alarms, GFCIs, full bedroom window egress operation, exhaust fan airflow, under-sink leaks, the range anti-tip bracket, and every supply stop.